murals

Interior of Tubchen monastery

When we started the pictorial integration in Tubchen monastery back in 2001, we adhered to the Western approach concerning the criteria for retouching wall paintings. This approach generally aims to avoid reconstructions. However, in 2003, an exception was granted with the approval of John Sanday Associates. This exception allowed for the reconstruction of substantial missing sections of two large Buddhas on the southern side of Tubchen and a portion of the upper decoration on the northern side of the East wall. The decision was made to enhance the visibility of the remaining pictorial cycle, ultimately bringing cohesion to the entire paint layer, particularly in the upper section.

the early end

The entire Lomanthang community found itself perplexed when the conservation work at Tubchen Gonpa concluded in 2004. The absence of further reconstructions left the entire lower section of the wall paintings covered with plaster below the paint layer. Bodhisattvas and Buddhas were depicted without their lower extremities, devoid of lotus flowers, and missing scenes, while the protective deities at the very bottom remained unreconstructed. For the community, the notion of leaving these parts unpainted seemed inconceivable and nonsensical.

Regardless of the community’s requests, the focus shifted to the conservation of Jampa Lhakhang while the project in Tubchen Gonpa was deemed complete, at least through the lens of Western perspectives.

a new beginning

Somehow things changed, and I changed as well. And when the local community asked once more to paint the missing part, the sponsors said yes, and so did I. Since 2011, regardless of all critics from the western world of academics, a reconstruction program was set up by The American Himalayan Foundation in order to complete all the missing wall paintings in Tubchen monastery and more than 150 square meters of lost paintings are being reconstructed following the XV century style (more than 340 square meters if the new north wall will be painted as well). Furthermore, with an accurate documentation, we have been mapping the locations of every reconstruction, so as to leave a record at the end of the project for future generations to understand where was the original artwork and where was the interpretation.

Here I would like to thank Samanta Ezeiza, who was my assistant to the project and who has worked tirelessly for the first two seasons.

To close this introduction, I would like to stress the importance that a a conservation philosophy should be shaped according to the culture’s needs and one single theory of conservation should not exist even though some principles could coexist. Cultures worldwide are very different and so should be the concept of conservation, if the latter is meant to be truly preserving a living cultural heritage site.

the making of new wall paintings in tubchen monastery

preparatory drawing
transfer of the sketch to the wall
painting the new dawing
matching the new paint with the old
01  /  preparatory drawing
02  /  sketch transfer
03  /  painting
04  /  ageing
keyboard_arrow_left
keyboard_arrow_right

some trivia

a step-by-step summary

ABOUT THE MONASTERY
Tubchen monastery's assembly hall measures roughly 22 by 28 meters and its height is about 7.4 meters. Consecrated in 1472 is an example of a seamless mix of XV century styles, from Newari to Tibetan to Chinese. More than half of the pictorial cycle was destroyed either by earthquake, water leakage and rising damp.

tubchen monastery plan

EAST WALL
Originally it hosted nearly 163 square meters of paint. Nowadays only a bit more than 100 square meters are left. Most of the damages here were caused by rising damp from the outside debris of mud and clay and from water infiltrations on the northern side of the wall. Near the entrance door there are 2 complete sections of wall paintings, which became the major source for organising the reconstruction programme.

SOUTH WALL
Originally it hosted nearly 207 square meters of paint. Nowadays only a bit more than half of the original paint is left and more than 110 square maters to paint anew. Most of the damages on this side were caused by rising damp due to stables attached to the monastery all along the south wall. Furthermore water infiltrations had destroyed a section on the western side.

tubchen monastery south wall elevation

WEST WALL
This is the wall where most of the big statues are placed. Hence it is difficult to surmise how many square meters there were here, even though we could think of the whole wall painted. At present less than 40 square meters are visible while a good amount is covered by recent over paintings and the large throne of the statues. Only 25 square meters should be painted anew here.

NORTH WALL
The original north wall has less than 15 square meters of murals left. A newer wall was built a bay inwards after an earthquake destroyed the majority of the original wall. It is the will of the locals to rebuild the wall as it was before and complete the whole pictorial cycle. If it will happen, there will be more than 190 square meters to paint anew.

tubchen monastery west elevation

the documentary

an intimate perspective